R E L I A N C E - I G S S I N S T A L L A T I O N M A N U A L

WHEN REGLAZING FROM THE INTERIOR. Remove interior wedge, remove old glass and clean

glazing pocket of any debris or glass and reglaze per glazing instruction on pages 13 thru 16.

WHEN REGLAZING FROM THE EXTERIOR FOLLOW STEPS R.1 THRU R.5

R.1 Carefully remove horizontal face covers surrounding the lite of glass to be deglazed. SEE FIGURE 48

R.2 Remove lower section of upper horizontal as shown in FIGURE 49, page 42.

R.3 Remove lite of glass and existing interior gaskets from the opening. Clean debris and sealant from the

framing members.

R.4 Install GP-101 gaskets into framing. Set new lite of glass, centered in opening.

R.5 Install IW-131 or IW-132 reglaze leg. Set in continuous bead of sealant and attach with FS-55 fastener

@ 12" o.c.,cap seal all fasteners. See FIGURE 50, page 42.

WHEN REGLAZING SSG FROM EXTERIOR FOLLOW STEPS R.6 THRU R.12

R.6 Carefully remove horizontal face caps surrounding the lite of glass to be deglazed. SEE FIGURE 48.

R.7 Remove pressure plate and isolator gasket from top of damaged lite at exterior glazed . AT

interior glazed; remove lower section of upper horizontal. SEE FIGURE 49, page 42.

R.8 Vertical structural silicone joints must be cut to remove broken lite of glass. SEE FIGURE 51,page 42.

R.9 Remove lite of glass and existing interior gaskets from the opening Clean debris and sealant from the

framing members and horizontal pressure plates.

R.10 Install GP-101 gaskets into framing. Set new lite of glass, centered in opening.

SEE FIGURE 52, page 42.

R.11 Re-install new GP-108 isolator gasket across face of horizontal and bridge. Seal per instructions page 28.

R.12 Reattach pressure plate using FS-322 fasteners. Torque fastener to 60 in/lbs. Seal ends of pressure

plates to vertical face or joints as shown on page 15. Reinstall face cap allowing equal gap at each end.

Pry Bar