Manual 0-5057

7-7

TORCH MAINTENANCE

TORCH MAINTENANCE

PAK 200

5. Unscrew the torch adaptor from the Torch Head

assembly. Slide the torch adaptor back over the
leads to expose the plasma (+), secondary, coolant
supply (-), and coolant return connectors.

Positioning Tube

Torch Adaptor

Lead Connections

A-00663

Bushing

Pinion Assembly

Machine

Torch Head

Figure 7-7: Torch Mounting Assembly

6. Disconnect the plasma (+), secondary, coolant

supply (-), and coolant return connectors to allow
removal of the Torch Head. Note the location of the
torch leads insulator which separates the negative
and positive leads.

Plasma Lead (+)

Coolant Return Lead

(LH Threads)

Secondary Lead

Coolant (-)

Supply Lead

A-02198

Figure 7-8: Torch Head Removal

B. Reassembling Machine Torch Assembly

NOTE

Verify that the small rubber duck valve is in

torch plasma fi tting.

1. Remove the rigid insulator from the old Torch Head

Assembly from between the layers of Estermat
paper.

2. Slide the rigid insulator between the layers of

Estermat paper on the replacement Torch Head
Assembly (see NOTE).

NOTE

Over a period of time there may be a breakdown

of the Estermat paper causing the Torch Head

to short out if the rigid insulator is not installed.

Two Layers Of

Estermat Paper

Rigid Torch

Leads Insulator

A-01577

Figure 7-9: Rigid Insulator Installation

3. Secure the rigid insulator in place with electrical

tape.

4. Slide replacement shrink on tubing on leads.

5. Connect the plasma (+), secondary, coolant supply,

(-) and coolant return connectors.

6. Secure leads and tubing with single layer of electri-

cal tape.

7. Slide the torch adapter down over the leads and

screw the adaptor securely onto the back of the
Torch Head assembly.

8. Slide the positioning tube down over the leads and

thread it into the torch adaptor on the Torch Head
assembly.

9. Apply tape to the torch leads sleeving at the back

end of the positioning tube.

10. Position shrink on tubing over the tape and shrink.

11. Install the front end torch parts.