4.10 Connecting the 920 Absorber Module to the remaining components

■■■■■■■■■■■■■■■■■■■■■■

74

■■■■■■■■

920 Absorber Module

4.10

Connecting the 920 Absorber Module to the remain-
ing components

Three capillaries are routed out at the right side of the Combustion IC sys-
tem.

The capillary connected to port 4 of the Dosino for ultrapure water is
marked with a blue colored sleeve.

The capillary connected to the outlet of the Metrosep A Trap 1 –
100/4.0 is marked with a yellow colored sleeve.

The thicker capillary installed at the inlet of the absorber tube is routed
out under the door.

4.10.1

Connecting the Combustion Module inlet: water infeed

Connecting the capillary for the water infeed at the inlet of
the combustion tube

1 Feeding the capillary into the Combustion Module

Feed the capillary with the blue colored sleeve into the inside
through the round opening up on the left side wall of the Combus-
tion Module and route it to the right side of the Combustion Module
(see Chapter "Installing the Combustion Module after transportation
or storage" in the Combustion Module operating instructions
).

2 Shortening the capillary

Shorten the capillary using the capillary cutter so that it can be con-
nected to the combustion tube's inlet easily.

3 Connecting the capillary

Three connections are located at the combustion tube's inlet: