SNAP-LOC 24

50

INSTALLATION OF GUTTER FLASHING

(CONT.)

2. Attach the SSR Gutter Support to the panel rib every other panel (48" O.C.) with two (2) #12-14

Self Driller XL screws. A section of Double Bead Tape Sealant is placed on the panel rib where the
SSR Gutter Support is fastened. A transit or a wire line should be used to align the SSR Gutter
Supports at a set distance from the wall. The SSR Gutter Supports can be adjusted as much as 1" to
allow the gutter to be installed in a straight line, even if the edge of the roof is not perfectly aligned.

3. Place a continuous strip of Double Bead Tape Sealant along the back lip of the Snap-Loc

Sculptured Gutter and remove the paper backing.

4. Prepare the first gutter section with a Snap-Loc Gutter End. Consider rake to gutter connection

for proper placement of Snap-Loc Gutter End. Use Double Bead Tape Sealant to seal between
the Snap-Loc Gutter End and the gutter flashing. Fasten with eight (8)

1

/

4

-14 x

7

/

8

" Stitch XL

screws or Pop Rivets.

SSR GUTTER SUPPORT

#12-14 SELF DRILLER XL

SSR SCULPTURED RAKE

(OFF MODULE)

WIRE LINE FOR

ALIGNMENT

SNAP-LOC

GUTTER END

DOUBLE BEAD
TAPE SEALANT

SNAP-LOC

SCULPTURED GUTTER

POP RIVETS

#12-14 SELF DRILLER XL

SNAP-LOC 24 PANEL

SSR GUTTER SUPPORT
DOUBLE BEAD TAPE SEALANT