Snap-loc 24, Installation of panel – Metal Sales Snap-Loc 24 Installation User Manual
Page 41

© Metal Sales Manufacturing Corporation / Subject to change without notice. 10/99
SNAP-LOC 24
40
INSTALLATION OF PANEL
(CONT.)
BEND LINE
CUT LINE
A
3"
TERMINATING
SNAP-LOC 24 PANEL
LAST FULL PANEL
A
STEPS
1. When the roof panel installation reaches the opposite end of the roof, the last panel run may need
to be field modified to attach to the Floating Rake Angle along the rake.
2. Measure the distance between the leg of the last full panel run and the vertical leg of the Floating
Rake Angle at the eave, endlap, and peak (Dimension "A").
3. Determine if a full panel will fit between the last full panel run and the Floating Rake Angle. In
most cases it will not fit. If the full panel will fit, then continue with the installation of the roof.
When the last panel is installed the leg of the male side must fit flush with the Floating Rake Angle.
4. If a full panel is too wide to fit between the last full panel run and the Floating Rake Angle, a panel
will have to be field-cut and bent to simulate the male leg.
5. Use the dimension taken between the last full panel run and the Floating Rake Angle and mark a
roof panel. Cut the panel flat 3" wider than the mark to allow for the correct height of a field bent
vertical leg.
TERMINATION OF PANEL
Note:
Minor ribs in Snap-Loc 24 panel
are not shown for clarity reasons.