Executes custom actions

Sends notifications

Power cycle servers

To power cycle servers

1.

Open the infrastructure orchestration console, self service portal, or organization administrator
portal

2.

Select the Services or My Services tab

3.

Select a service and click Details or View Details

4.

From the Actions or Server Actions list, select Power cycle servers

During this operation, infrastructure orchestration:

Validates the request

Checks that the servers to be powered off are in the state that is allowed to be stopped

Executes custom actions

Starts the PowerOff process for all the selected servers

Executes custom actions

Starts the PowerOn process for all the selected servers

Executes custom actions

Sends notifications

Change lease operation

To modify the starting or ending dates of the service, or to extend or reduce the lifetime of the
service, use the Change Lease Period operation.

To change a service lease period

1.

Open the infrastructure orchestration console, self service portal, or organization administrator
portal

2.

Select the Services or My Services tab

3.

Select a service and click Details or View Details

4.

From the Actions or Server Actions list, select Change service lease period.

During this operation, infrastructure orchestration:

Validates the request for a new lease period

Modifies servers (server blades or virtual machine hosts) allocation for a new lease period

Modifies network and IP addresses allocation for a new lease period

Modifies disk allocation for a new lease period

Obtains approval to extend a lease

NOTE:

Reducing a lease period does not require approval.

Executes custom actions

Sends notifications

After successfully completing a Change Lease Period operation, infrastructure orchestration modifies
the lease period for the infrastructure and updates the allocation of each resource for the new lease
period. If a resource is not available or an administrator rejects the request, the Change Lease
Period operation fails.