beautypg.com

A.O. Smith 3400 User Manual

Page 36

background image

36

DIRECT VENTING: VERTICAL TERMINATION

Installation must comply with local requirements and with the

National Fuel Gas Code, ANSI Z223.1 for U.S. installations or

CSA B149.1 for Canadian installations.
VENT/AIR TERMINATION LOCATIONS:
Follow these guidelines for locating the vent/air terminations:
1. Make sure the total length of piping for vent or air do not

exceed the limits mentioned in Table 13 and Table 14 on

Page 37.

2. The vent must terminate at least 3 feet (0.9 m) above the

highest place in which the vent penetrates the roof and at

least 2 feet (0.6 m) above any part of a building within 10

feet (3 m) horizontal.

3. The air piping must terminate in a down-turned 180° elbow,

using a mesh screen.

4. The vent piping must terminate in an up-turned rain cap as

shown in Figure 34. When the vent termination uses a rain

cap as illustrated in Figure 34, maintain at least 36" (914

mm) above the air inlet.

5. Locate terminations so they are not likely to be damaged by

foreign objects, such as stones or balls, or subject to buildup

of leaves or sediment and also not blocked or restricted by

snow accumulation.

6. If installing both intake air and vent piping in a Direct Vent

configuration vertically through the roof; ensure that all

exterior vertical clearance requirements shown in Figure 36

are being maintained. These clearances and those cited by

local and national codes must be maintained.

NOTE: On flat roof installations the intake air and the vent

terminations must be a minimum of 24 inches (60 cm) above any

parapet, vertical wall or structure within 10 feet (3 m) horizontally.

See Figure 36.

FIGURE 34. PVC/CPVC AIR/VENT TERMINATION -

VERTICAL

PREPARE ROOF/WALL PENETRATIONS

1. Air pipe penetration:
Cut a hole for the air pipe. Size the air pipe hole as close as

desired to the air pipe outside diameter.
2. Vent pipe penetration:
Cut a hole for the vent pipe. For either combustible or

noncombustible construction, size the vent pipe hole with at least

a 1/2 inch clearance around the vent pipe outer diameter:

• 7½ inch (178 mm) hole for 6 inch (152 mm) vent pipe
• 8½ inch (203 mm) hole for 7 inch (178 mm) vent pipe

Insert a galvanized metal thimble in the vent pipe hole (when

required by local codes).
3. Space the air and vent holes to provide the minimum spacing

shown in Figure 34 and Figure 35.

4. Follow all local codes for isolation of vent pipe when passing

through floors, ceilings, and roofs.

5. Provide flashing and sealing boots sized for the vent pipe

and air pipe.

FIGURE 35. STAINLESS STEEL AIR/VENT TERMINATION -

VERTICAL

FIGURE 36. VERTICAL TERMINATION - FLAT ROOF

CLEARANCES

This manual is related to the following products: