LumaSense Technologies BoilerSpection-SD User Manual
Page 21
BoilerSpection HD/SD Manual
BoilerSpection Installation Guide 21
1-2 weeks prior
Pull and terminate communication cables from camera mounting locations to field
switch and from field switch to control room.
Install air lines.
Install electrical conduit and pull main electrical supply lines.
Installation week:
Stage system components at each camera location.
Install computers/servers in computer rack room or control room.
Attached mounting plates (weld-on or bolt-on).
Slide camera wall box into mounting plate and tack weld Camera system in position.
Verify the aim of the camera using local laptop or local video monitor (or lasers in the
case of an installation during an outage).
Once aim is verified, fully weld the wall box in to the mounting plate.
Mount controls and air filtration sub-systems.
Connect all electrical, air, and communications cables.
Inspect all workmanship.
Commission full system functionality testing and document.
Train local personnel.