8 MAINTENANCE

NOTE

The operations outlined in this chapter are to be

performed by qualified maintenance personnel only.

8.1 Maintenance Schedule

Table 8-1: Preventative Maintenance Schedule

Item

Maintenance Interval

Reference Section

TEST functions

Check every month

Table 9-1

Zero/Span Calibration

Weekly or as needed

Section 7

Zero/Span checks

Daily

Section 7, Table 6-2

Particulate Filter

Weekly as needed

Figure 8-1

Zero air canister

Refill every 3 months

Section 8.4

Zero Air DFU filter

Change every 12 months

Section 8.4

Reaction cell cleaning

Clean annually and clean as necessary

Section 8.6, Figure 8-3

Sample Flow

Check every 6 months

Figure 8-3, Section 9.2.2

Pneumatic Lines

Examine every 12 months, clean if
necessary

Figure 8-3

Factory Calibration

Calibrate each year or after repairs

Section 9.1.6

Leak Check

Check every year

Section 8.8

Pump Diaphragm

Change annually

8-1