14.3 Startup Procedures

The procedure to start the UpS is shown in Steps 1-5.

STEP 1

Turn on the control power supply switch.

(Figure 14.1) and ensure the operation lock is

set to operATIon. (Figure 13.1 - 1)

STEP 2

wait for a few seconds.

STEP 3

press the “rUn” button for at least 0.5

seconds.
ConVerTer leD is “on” and InVerTer

LED flashes.

CONVERTER

INVERTER

UPS

AC OUTPUT

BATTERIES

BYPASS INPUT

DISCHARGE

EQUAL CHARGE

FLOAT CHARGE

BYPASS

AC INPUT

AC

SWITCH

SYSTEM INITIALIZE

CONVERTER

INVERTER

UPS

AC OUTPUT

BATTERIES

BYPASS INPUT

DISCHARGE

EQUAL CHARGE

FLOAT CHARGE

BYPASS

AC INPUT

AC

SWITCH

BYPASS

PRESS ‘RUN’ SWITCH

CONVERTER

INVERTER

UPS

AC OUTPUT

BATTERIES

BYPASS INPUT

DISCHARGE

EQUAL CHARGE

FLOAT CHARGE

BYPASS

AC INPUT

AC

SWITCH

BYPASS

UPS STARTING

WAIT FOR A WHILE