beautypg.com

3 anchor bolts – Toshiba G8000 User Manual

Page 36

background image

28

G8000 Series Installation and operation Manual

G8000 Series Installation Manual

26

10.3 Anchor Bolts

Install the anchor bolts to secure the UpS on the floor. See Figure 10.2 for anchor bolt installation detail.

Use 12mm (1/2”) diameter anchor bolts. There are 16mm (5/8”) diameter holes provided in the UpS base.

See Figure 10.3 for the hole locations and dimensions for the specified UpS models.

FIGURE 10.2

ANCHOR BOLT INSTALLATION DETAIL

FIGURE 10.3

HOLE LOCATIONS/DIMENSIONS

ON BOTTOM OF UPS

4 of 16mm-diameter

(5/8”) screw holes

Anchor bolt

4 screw holes

(Side View)

Front

back

551mm

(21” 11/16)

1,170mm (46” 1/16)

< 100kVA (T80S3K10KK6XSNH) >

< 150/225kVA >

4 x 12mm-Dia. (1/2”)

551mm

(21” 11/16)

754mm (29” 11/16)

< 100kVA (T80S3K10KK6XS2H) >

Front

back

4 x 12mm-Dia. (1/2”)

572mm

(22” 1/2)

572mm

(22” 1/2)

572mm

(22” 1/2)

650mm

(25” 19/32)

< 250/300kVA >

8 x 12mm-Dia. (1/2”)

Front

back

10.3 Anchor Bolts

Install the anchor bolts to secure the UPS on the floor. See Figure 10.2 for anchor bolt installation detail.

Use 12mm (1/2”) diameter anchor bolts. There are 16mm (5/8”) diameter holes provided in the UpS base.

See Figure 10.3 for the hole locations and dimensions for the specified UPS models.

FIGURE 10.2

ANCHOR BOLT INSTALLATION DETAIL

FIGURE 10.3

HOLE LOCATIONS/DIMENSIONS

ON BOTTOM OF UPS