Electrician
6
Mounting the inverter
6.1
Selecting the installation location
NOTE
The maximum flow rate of the cooling air is different for each inverter type:
•
Powador XP200-HV TL: 4040 m
3
/h
•
Powador XP250-HV TL: 4040 m
3
/h
•
Powador XP350-HV TL: 5460 m
3
/h
›
Keep this value in mind when you select the installation location.
Floor
•
The floor must have adequate load-bearing capacity
(a separate, solid basement may be necessary).
•
The building material must meet the requirements of buil-
ding material class B1 (“Flame-resistant Building Materials”,
in accordance with DIN EN 13501-1).
•
The floor must consist of non-cracked concrete.
Room
•
Permanent access to the installation location for installa-
tion and service purposes must be possible.
•
The room must provide enough space to work at the inver-
ter in case of maintenance (e.g. exchange of filter mats).
•
The room must provide operating conditions according to
the technical specification.
•
The necessary amount of cooling air must be available at
the installation location.
•
Adequate air circulation through the inverter must be gua-
ranteed. Air inlets and outlets must not be blocked.
•
Thermal short circuits must be excluded.
Figure 7: Ventilation for the inverter
"
Ensure that all regulations for emergency situations are considered.
"
Make sure that the escape routes (according to local requirements) are not blocked in any circumstance.
"
Do not install the inverter in a room where there is a risk of explosion.