3.8 Wiring the Power Supply/Regenerative Unit Connector (CNA)
E-30
3.8 Wiring the Power Supply/Regenerative Unit Connector (CNA)
Use the following procedure when connecting the SERVOPACK to the power supply/regenerative unit connector.
1. Remove the connector from the SERVOPACK.
Make sure to remove the connector from the SERVOPACK when wiring.
2. Strip the outer coating.
Straighten the wire core with your fingers to prevent the wires from unwinding.
3. Open the wire terminal on the power supply connector housing (plug) with the tool (lever for wiring)
using the procedure shown in Fig. A or B.
• Insert the connection hook end of the provided tool into the slot as shown in Fig. A.
Tool must be purchased by the customer.
• Use a standard flat-blade screwdriver (blade width of 2.5 to 3.0 mm (0.09 to 0.12 in)). Put the blade into the
slot, as shown in Fig. B, and press down firmly to open the wire terminal.
Either the procedure shown in Fig. A or B can be used to open the wire insert opening.
4. Insert the wire core into the opening and then close the opening by releasing the tool hook or remov-
ing the screwdriver.
Wire Size
• Observe the following precautions when wiring connectors for power supply/regenerative unit and
for motor main circuit cable.
• Remove the connectors from the SERVOPACK prior to wiring.
• Insert only one wire per terminal on the connectors.
• Make sure that the core wire is not electrically shorted to adjacent core wires.
Item
Wire Size
Conductor
Size
Braided wire
AWG14 to AWG22
Single wire
φ1.6mm to φ0.65mm
Sheath Dimension
φ3.8mm to φ1.7mm
CAUTION
9 to 10 mm
fig A
fig B
Tool Type: J-FAT-OT