• Unlock conductor entry 8 with a screwdriver and insert the insulated conductor of the

wire into the conductor entry.

• Unlock conductor entries 6 and 7 with a screwdriver and insert the insulated conductors

of the connection cable into the conductor entries. Observe the pin assignment.

• Insert the eight-pole plug into pin row A in terminal X8.

4. For connection to the pin group Analog current input 3, perform the following steps:

• Unlock conductor entry 4 with a screwdriver and insert the insulated conductor of the

wire into the conductor entry.

• Unlock conductor entries 2 and 3 with a screwdriver and insert the insulated conductors

of the connection cable into the conductor entries. Observe the pin assignment.

• Insert the eight-pole plug into pin row B in terminal X8.

5. On the connection cable, mark the terminal and the pin row to which the connection cable is

assigned. Use the supplied cable tie with caption field.

6. Write down the terminal assignment on the supplied supplementary sheet.

Connecting a Sensor to the Analog Voltage Input

Additionally required material (not included in the scope of delivery):

☐ 1 sensor
1 connection cable (see Section 6.3 "Cable Requirements", page 30)

Requirements:

☐ The sensor must be technically suitable for connection to the analog inputs (see Section 9,

page 84).

The connection cable must be prepared for connection to the multipole plug (see Section 6.5,

page 33).

Figure 17: Pin assignment for pin group Analog voltage input 4

Pin

Signal

Explanation

B5

V+

Voltage input

B6

Not assigned

Reserved for future applications

B7

V−

Voltage return

B8

GND

Shield ground