beautypg.com

Redundancy installation – Comtech EF Data XSAT-7080 User Manual

Page 102

background image

XSAT7080 X-Band Transceiver

Revision 0

5-25W Installation

MN/XSAT7080.IOM

A–20

A.5.4 R

EDUNDANCY

I

NSTALLATION

Notes:

1. Redundant XSAT’s require two AS/0414 pole mount kits.
2. After the two pole brackets have been attached to the pole, they need to be properly

spaced in relation to each other. This spacing is established with the switch-
mounting bracket (1, figure A-11).

Figure A-18. Installation of

Redundant Brackets










Step

Procedures

1

Place two springnuts (7, figure A-11) in each unistrut bracket (1, Figure A-1).

2

Center the bracket (1, figure A-11) horizontally on the top unistrut bracket
(1, figure A-1) and fasten with two bolts (8, figure A-11) flat washers (5), and split
washers (6).

3

Loosen lower unistrut bracket and position so the lower holes in the bracket are
aligned vertically with the center of the lower unistrut bracket .

4

Position the springnuts as required. Secure bracket (1, figure A-11) to the unistrut
bracket (1, figure A-1) using two bolts (8, figure A-11), flat washers (5), and split
washers (6). Tighten the tension bracket (2, figure A-1).

5

Slide two springnuts (5, figure A-1) into the right-side of each of the two channels
of the unistrut brackets (1, figure A-1).

6

Place one bracket (1, figure A-2) against the right side of the switch bracket
(1, figure A-11). Position the springnuts to line up with four holes in bracket
(1, figure A-2). Secure using screws (3, figure A-2).

7

Repeat steps (5) and (6) for the left bracket (1, figure A-2).