2 dc system startup procedure, Ions, Dc system startup – Artesyn Centellis 2000 Shelf Release 3.0 Installation and Use (May 2014) User Manual

Page 93: Procedure, System installation

background image

System Installation

Centellis 2000 Shelf Release 3.0 Installation and Use (6806800L99G)

93

7. Check the AC PSU Status LED and take the appropriate actions as listed in the table

below.

3.3.3.2

DC System Startup Procedure

Depending on the system configuration, the actual powering up may take up to 3 minutes.

Make sure that the system has been placed in a location at room temperature for at least
24 hours before powering it up.

1. Put on an ESD wrist strap.

2. Connect the strap to the shelf by attaching the front or rear ESD jack/ESD snap.

3. Mount the grounding cable to the Protective Earth connection lug if not done

already.

PSU Status LED

Status

LED (red) off

Reason: The power is disconnected.
Action: Turn off the feed power and attach the power cables at the
power connector .

LED (red) on
LED (green) off

Power supply is in a failed state.

LED (red) off
LED (green) on

The power is connected correctly.