beautypg.com

2 example 2: connection of 5 base units, 6commissioning, 3 connection examples – Pilz PNOZ mm0.2p User Manual

Page 35

background image

Pilz GmbH & Co. KG, Felix-Wankel-Straße 2, 73760 Ostfildern, Germany
Telephone: +49 711 3409-0, Telefax: +49 711 3409-133, E-Mail: [email protected]

6-11

6.3

Connection examples

6

Commissioning

6.3.1.2

Example 2: Connection of 5 base units

Example 2: Connection of 5 base units

6-

Anschlussbeispiel_Verbindungsmodul_Reihenschalitung_5_Basisgeräte_Text

The reaction times are calculated in the same way as application exam-

ple 1. After pressing S1 on Base 1, the semiconductor outputs switch

after the following reaction times t

SUM

:

O0 on Base 2: 69 ms

O1 on Base 3: 104 ms

O0 on Base 4: 139 ms

O0 on Base 5: 104 ms

_Dummy-Vorlage

I3 I6

Base 1

Base 2

Base 3

S1

K3

Base 4

Base 5

I4 I6

K2

O0

O1

K4

O0

K5

O0