3 commissioning the pnozmulti safety system, 1 load project from chip card, 6commissioning – Pilz PNOZ mm0.2p User Manual
Page 27: 2 preparing for operation
Pilz GmbH & Co. KG, Felix-Wankel-Straße 2, 73760 Ostfildern, Germany
Telephone: +49 711 3409-0, Telefax: +49 711 3409-133, E-Mail: [email protected]
6-3
6.2
Preparing for operation
6
Commissioning
6.2.3
Commissioning the PNOZmulti safety system
Commissioning the PNOZmulti safety system
6-
Verdrahtung_multi_Basis_Betr_erstes_Mal_mini_multi_BA
Procedure:
Wire the inputs and outputs on the base unit in accordance with the
circuit diagram.
Connect the supply voltage:
– Supply voltage for the units:
– Terminal A1: + 24 VDC
– Terminal A2: 0 V
– Supply voltage for the semiconductor outputs:
– 24 V terminal: + 24 VDC
– 0V terminal: 0 V
Note: The supply voltage for the semiconductor outputs must always be
present, even if you are not using the semiconductor outputs.
Verdrahtung_multi_Basis_Betr_Erweiterungsmodule nicht abstecken während Betrieb_BA
6.2.3.1
Load project from chip card
Load project from chip card
6-
Verdrahtung_mini_multi_Basis_Betr_erstes_Mal_von_Chipkarte_BA
Procedure:
Insert the chip card containing the current project into the card slot on
the base unit.
Switch on the supply voltage. The LC display shows the project
name, CRC sum and the date the project was created. Please check
this information.
Load the project by pressing the rotary knob. For the project to be
downloaded, the rotary knob must be held down for between 3 and 8
seconds. Once the project has been successfully downloaded, the
status of the inputs and outputs will be shown on the display.
CAUTION!
Do not connect or disconnect expansion modules and termina-
tors during operation.