Field operation, Monitor operation, Field operation monitor operation – Great Plains YP1625 Operator Manual User Manual
Page 42

38
YP1225 and YP1625
Great Plains Manufacturing, Inc.
401-226M-A
03/12/2012
Field Operation
Perform all steps in “Pre-Start Checklist” on page 18
and “Field Setup Checklist” on page 36.
Note: Use Depth Control mode. If tractor 3-point hitch
control is set for Load Control, hitch movement
may cause changes in row unit depth resulting in
uneven depth control.
Null4-AAC:
FigureSpacer:
FigureSpacer:
FigureSpacer:
Monitor Operation
For monitor operation in the field, refer to the DICKEY-
john ® manual supplied with this unit, and the Seed Rate
manual.
First Pass Operation Checklist
Page
1. Set planting rate.
2. Unfold marker on next-row side.
3. Set fan hydraulic circuit to low flow, engage
circuit. Gradually adjust fan hydraulic flow to
obtain (normally) 3800 rpm.
4. Engage optional hydraulic seed drive via
seed monitor.
-
5. In the CLUTCH cluster of the CFM, set all
switches, including Master, to ON.
6. Pull forward, lower planter, and begin plant-
ing for a short distance.
7. Stop. Assess planting depth, seed spacing,
press wheel operation and fertilizer applica-
tion (if in use)
8. Make necessary adjustments
FigureSpacer:
Figure 46
CFM: Planting Configuration
28491
Sharp Field Turns Checklist
Page
1. Fold marker
2. Raise planter
3. Make turn
4. Lower planter
5. Unfold marker on next-row side.
6. Resume planting.
Suspending Planting Checklist
Page
1. Stop tractor
2. Fan hydraulic circuit to Float or Neutral
3. Fold Marker
4. Raise planter
Ending Planting Checklist
Page
1. Suspend operations as above, then
2. Fold planter
3. Install transport locks
4. Lights ON
-
5. Transport