38

YP1225 and YP1625

Great Plains Manufacturing, Inc.

401-226M-A

03/12/2012

Field Operation

Perform all steps in “Pre-Start Checklist” on page 18
and “Field Setup Checklist” on page 36.

Note: Use Depth Control mode. If tractor 3-point hitch

control is set for Load Control, hitch movement
may cause changes in row unit depth resulting in
uneven depth control.

Null4-AAC:

FigureSpacer:

FigureSpacer:

FigureSpacer:

Monitor Operation

For monitor operation in the field, refer to the DICKEY-
john ® manual supplied with this unit, and the Seed Rate
manual.

End of “Field Operation

First Pass Operation Checklist

Page

1. Set planting rate.

45

2. Unfold marker on next-row side.

41

3. Set fan hydraulic circuit to low flow, engage

circuit. Gradually adjust fan hydraulic flow to
obtain (normally) 3800 rpm.

39

4. Engage optional hydraulic seed drive via

seed monitor.

-

5. In the CLUTCH cluster of the CFM, set all

switches, including Master, to ON.

40

6. Pull forward, lower planter, and begin plant-

ing for a short distance.

7. Stop. Assess planting depth, seed spacing,

press wheel operation and fertilizer applica-
tion (if in use)

8. Make necessary adjustments

44

FigureSpacer:

Figure 46

CFM: Planting Configuration

28491

Sharp Field Turns Checklist

Page

1. Fold marker

41

2. Raise planter

22

3. Make turn

4. Lower planter

22

5. Unfold marker on next-row side.

41

6. Resume planting.

Suspending Planting Checklist

Page

1. Stop tractor

2. Fan hydraulic circuit to Float or Neutral

39

3. Fold Marker

41

4. Raise planter

22

Ending Planting Checklist

Page

1. Suspend operations as above, then

2. Fold planter

24

3. Install transport locks

25

4. Lights ON

-

5. Transport

27