beautypg.com

Transmig 250i installation/setup – Tweco 250i Transmig Inverter User Manual

Page 48

background image

TRANSMIG 250i

INSTALLATION/SETUP

INSTALLATION/SETUP 3-30

Manual 0-5187

NOTE

The regulator/flow meters used with argon based and carbon dioxide shielding gases are different. The

regulator/flow meter supplied is for argon based shielding gases. If carbon dioxide is to be used a suitable

carbon dioxide regulator/flow meter will need to be fitted.

NOTE

All valves downstream of the regulator must be opened to obtain a true flow rate reading on the outlet

gauge. (Welding power source must be triggered) Close the valves after the pressure has been set.

Installation

1. Remove cylinder valve plastic dust seal. Clean the cylinder valve outlet of impurities that may clog orifices and

damage seats before connecting the regulator.

Crack the valve (open then close) momentarily, pointing the outlet away from people and sources of ignition.

Wipe with a clean lint free cloth.

2. Match regulator to cylinder. Before connecting, check that the regulator label and cylinder marking agree and

that the regulator inlet and cylinder outlet match. NEVER CONNECT a regulator designed for a particular gas

or gases to a cylinder containing any other gas.

3. Connect the regulator inlet connection to cylinder or pipeline and tighten it firmly but not excessively, with a

suitable spanner.

4. Attach supplied gas line between the regulator output and the desired input at the rear of the power source.

MIG Spool Torch and TIG in the bottom fitting and regular MIG Torch in the top fitting.

Art # A-10239

Ensure that the gas

cylinder is secured to

a building pillar, wall

bracket or otherwise

securely fixed in an

upright position.

Figure 3-27: Attach gas line to proper inlet

5. To protect sensitive down-stream equipment a separate safety device may be necessary if the regulator is not

fitted with a pressure relief device.

Operation

With the regulator connected to cylinder or pipeline, and the adjustment screw/knob fully disengaged, pressurize as

follows:

1. Stand to one side of regulator and slowly open the cylinder valve. If opened quickly, a sudden pressure surge

may damage internal regulator parts.

2. With valves on downstream equipment closed, adjust regulator to approximate working pressure. It is recom-

mended that testing for leaks at the regulator connection points be carried out using a suitable leak detection

solution or soapy water.