Architectural, Rakewall with counter detail – Metal Sales Soffit Panel User Manual
Page 43

© Metal Sales Manufacturing Corporation / Subject to change without notice, effective 02/09.
42
ARCHITECTURAL
(Direct Fasten)
(Optional)
INSTALLATION NOTES
Z-Closure
Double Bead Tape Sealant
Fasteners (by others)
Roof Panel
Moisture Barrier (by others)
Rakewall
Counter Flashing
Pop-Rivet (1'-0" o.c.)
Tube Sealant
Pancake Head Woodscrew (1'-0" o.c.)
RAKEWALL WITH COUNTER DETAIL
1. If panel ends off module bend flat part of the panel up a minimum of 1", otherwise skip to the next note.
2. Apply a row of Double Bead Tape Sealant to the flat part of the panel next to the panel rib or vertical field bent leg.
3. Position Z-Closure over tape sealant and fasten to wood substrate with #10-12 x 1" Pancake Head Woodscrew, 12"o.c.
Fastener must penetrate through the Z-Closure, Tape Sealant, and panel.
4. Install Rakewall to the Z-Closure with
1
/
8
" x
3
/
16
" Pop Rivets at 12" o.c.
5. Install Counter Flashing, and fasten to parapet wall with appropriate fastener 12" o.c. Seal Counter Flashing to parapet
wall with Tube Sealant.
6. If two or more flashings are required, lap the flashing over the previously installed flashing by a minimum of 2" placing a
bead of Tube Sealant between the flashings and securing with pop rivets 2.5" o.c.
(Not available for Pro-Loc.)
3:12 Slope
Minimum