Carrier sub-assembly procedure, Carrier sub-assembly procedure -60 – JLG 460SJ ANSI Service Manual User Manual
Page 114

SECTION 3 - CHASSIS & TURNTABLE
3-60
– JLG Lift –
3120788
9. Retaining Ring (1I) installed into the groove provided
in the output Shaft (1A). This retaining Ring (1I)
should never be reused in a repair or rebuild.
EYE PROTECTION SHOULD BE WORN DURING THIS PROCEDURE.
10. A soft metal punch should be used to insure that this
retaining ring (11) is completely seated in the groove
of the Output Shaft (1A).
EYE PROTECTION SHOULD BE WORN DURING THIS PROCEDURE.
11. Upon completion of step 10, rap the internal end of
the Output Shaft (1A) twice with a piece of soft metal
rod. This will release the preload which was on the
bearings.
Carrier Sub-Assembly Procedure
1. Apply a coat of grease or petroleum jelly to Cluster
Gear bore.
2. lace sixteen Needle Rollers into Cluster Gear bore.
3. Place Spacer Washer into opposite side of Cluster
Gear and against Needle Rollers.