Chapter 4. Example Operations

100

TSU 600 User Manual

61200.076L2-1

TESTING EXAMPLE

If the example operations in the preceding pages were
followed, the TSU 600 is completely configured and
capable of passing data from the PBX and the DTE.
Prior to actually using the configuration to pass voice
and data, it is recommended to run tests on the circuit.

Testing consists of sending a test pattern from end to
end and checking for errors in the pattern. There are
two types of tests used to accomplish this.

• Send the pattern from one end and loopback the far

end.

• Send the pattern from both ends and check at both

ends.

Far End Looped Back Test

Two types of tests can be executed with the far end
looped. The first is a check of the network and the
network interfaces at both ends (QRSS). The second is
a check of the DTE port.

Network Interface Test

The Network Interface Test can only be run when a
full T1 is available (i.e., this cannot be used over
Fractional T1).

At the Main menu place the cursor on 4)TEST with the
number 4 or by scrolling. To activate the menu, again
press number 4 or Enter.

The unit displays the first two Test submenu items
with the cursor on 1)NETWORK TESTS (see Figure 4-
15). To activate, press number 1 or Enter.