HP SUM displays the nodes it finds in the Available Nodes field.

d.

Select the nodes you want to add from the Available Nodes section, and then click Add
Nodes.

e.

If you want to assign a baseline, select a Baseline, Additional Packages in the Baseline
to Apply field.

f.

In the Credentials section, select whether to Use current user credentials or Enter
administrator credentials (Windows only).

If you choose to enter administrator credentials, enter a username and password.

2.

Click Add.

In the Added Nodes section, HP SUM displays the nodes you selected.

3.

Click Cancel to go back to the Nodes screen.

Editing a switch

1.

From the Switches screen, highlight the switch, and then click Actions

→Edit.

2.

The Edit Switch procedure is the same as the Edit Node procedure.

To edit a node

1.

From the Nodes screen, highlight the node and then click Actions

→Edit.

2.

Change the items you want to edit:

Description

Type

NOTE:

Select the check box if you want HP SUM to automatically add Associated

Devices. (Not available for all node types.)

HP SUM displays the currently selected baseline and additional package. Use the
drop-down menu if you want to change these.

NOTE:

If you want to delete a baseline or additional package, the baseline or additional

package cannot be associated with a node. Associate a new baseline or delete the node
to delete a baseline.

Credentials

OS Management Options – None, Use SNMP, Agentless Management Service, Use
WBEM

Reboot Options – Reboot system, Reboot delay, Reboot message

Installation Options – Downgrade or rewrite versions

Force Options – Show firmware or software updates

3.

Click OK to accept the changes and return to the Nodes screen.

Aborting a switch update

1.

From the Switches screen, highlight the switch whose updates you want to cancel.

2.

Click Actions

→Abort.

Switch inventory

1.

From the Switches screen, highlight the switch on which you want to take inventory.

2.

Click Actions

→Inventory.

3.

The Switch Inventory procedure is the same as the Node Inventory procedure.

44