beautypg.com

Installation, 11 measurement setup for steam measurement – KROHNE OPTIBAR PC 5060 C EN User Manual

Page 24

background image

3

INSTALLATION

24

OPTIBAR PC 5060 C

www.krohne.com

04/2014 - 4003437201 - MA OPTIBAR PC 5060 C R01 en

3.11 Measurement setup for steam measurement

The following points should be observed in this application:

• The pressure transmitter should be connected via a siphon to protect the measuring cell

from non-permitted high temperatures.

• Siphon to be kept free of insulation.
• When using superheated steam, the siphon must be filled with water prior to start-up.

Figure 3-8: Measurement setup for steam measurement

1 Pressure transmitter
2 Shut-off valve
3 Siphon
4 Tapping point

.book Page 24 Friday, May 2, 2014 12:49 PM