7.3.4 Restarting the Self‑Test
In order to restart the self‑test, proceed as follows:
1. Disconnect the miniature circuit‑breaker and secure against re‑connection.
2. If a multi‑function relay is connected, switch off the multi‑function relay power supply.
3. Disconnect the Electronic Solar Switch from the inverter for 5 minutes and then connect it again.
4. Switch on the miniature circuit‑breaker again.
☑ The inverter is now in the initialization phase and you can restart the self‑test, as described in
section 7.3.1 "Starting the Self‑Test" (page 52) from step 3.