3 commissioning the inverter, Commissioning the inverter – SMA SB 3600SE-10 User Manual
Page 40

Procedure:
1. Determine the rotary switch position for your country and purpose. To do this, consult the
Technical Information "Overview of the Rotary Switch Settings" at
2.
Danger to life due to high voltages
• Ensure that the inverter is disconnected from all voltage sources and that the enclosure lid
is removed (see Section 10, page 54).
3. Set the rotary switches A and B to the required
position using a flat-blade screwdriver (blade
width: 2.5 mm).
☑ The inverter will adopt the setting after commissioning. This can take up to five minutes.
7.3 Commissioning the Inverter
Requirements:
☐ The inverter and the Battery Pack must be correctly mounted.
☐ The circuit breaker must be correctly rated.
☐ All cables must be completely and correctly connected.
☐ Unused DC inputs must be sealed using the corresponding DC connectors and sealing plugs.
☐ The country data set must be set correctly for the country or the purpose.
☐ The Battery Pack must have been pushed as far as possible to the right on the wall mounting
bracket and the protective cover must be over the Battery Pack.
☐ The inverter must be connected to the network.
☐ The inverter must be connected to the SMA Energy Meter or to another suitable energy meter.
Procedure:
1. Ensure that the DC load-break switch is turned to position OFF. This makes it possible to fit the
enclosure lid to the enclosure.
2. Attach the enclosure lid as follows:
7 Commissioning
SMA Solar Technology AG
Operating Manual
SB36-50SE-BE-en-11
40