Installation – Hypertherm HD3070 Plasma Arc Cutting System w/ Automatic Gas Console User Manual
Page 81
HD3070 with Automatic Gas Console
Instruction Manual
3-33
16
INSTALLATION
Control Cable
4X1
Preflow Gas Hose
(Red Band)
Shield Gas Hose
(Green Band)
Plasma Gas Hose
(Blue Band)
Control Cable
3X3
Preflow Gas Hose
(Red Band)
Plasma Gas Hose
(Blue Band)
Automatic Gas Console
Shield Gas Hose
(Green Band)
Off-Valve Assembly
Gas Lead Set
Figure 3-25 Gas Console to Off-Valve Assembly Interconnections
*Disregard these items, if system was ordered without the blow
back option.
Off-Valve Cable
*Blow Back Solenoid
(End user 120 VAC required.)
SV16
SV14
SV15
Plasma Hose
Figs 3-24 & 3-28
Shield Hose
Figs 3-24 & 3-27
*Blow Back Hose
Figure 3-24
SV16
SV15
SV14
14B
14C
14B
14A 14B
14C
14C
14B
14C
14D
14D
14D
14A
14D
14A
14A
14
15
16
17
Part Number
Length
128175
15 ft (4.6 m)
128176
20 ft (6.1 m)
128177
25 ft (7.6 m)
128178
30 ft (9.1 m)
128179
35 ft (10.6 m)
128180
40 ft (12.2 m)
128181
50 ft (15.2 m)
128182
75 ft (23 m)
128183
100 ft (30.5 m)