Chapter 4

ATCA-MF106 Installation and Use (6806800M62B)

55

Board Exchange

4.1

Introduction

This chapter describes how to install the ATCA-MF106 board and includes the following
information:

Before installation

Installing the board in a shelf

Starting up the board

Removing the board

Operation

4.2

Before Installation

This section provides the following information:

Requirements

Unpacking and inspecting the board

4.2.1

Requirements

Before you power up the board, calculate the power needed according to your system
configuration.

The system is shipped with pre-installed ATCA-MF106 boards. You have to observe the
following procedures when ordering a board as a spare part or exchanging a board.

For more information on installing and replacing the ATCA-MF106 board and for a
description of replacement scenarios, see the Centellis 2000 Shelf-DC Installation and Use
manual.