beautypg.com

1 load modified project from chip card, 2 load modified project via integrated interface, 4 connection – Pilz PNOZ m1p base unit User Manual

Page 22: Connection

background image

Commissioning

Operating Manual PNOZ m1p (ETH)
20878-EN-12

22

Download modified project to the control system PNOZmulti

Load modified project from chip card
To download data via chip card, the existing configuration data must first be deleted (gener-
al reset of device).
Procedure:

}

Switch off the supply voltage.

}

Disconnect all the output terminals.

}

Jumper OA0-I19 on the base unit.

}

Switch on the supply voltage.

When the "DIAG" LED on the base unit flashes, the memory has been cleared. The project
data can now be downloaded:

}

Switch off the supply voltage.

}

Remove the old chip card from the chip card slot on the base unit.

}

Remove the jumper from OA0-I19 on the base unit.

}

Insert the chip card containing the current project into the card slot.

}

Switch on the supply voltage.

Load modified project via integrated interface
Proceed as described for the initial commissioning

Connection

Supply voltage

AC

DC

For the safety system

(connector X7)

A1

+ 24 V DC

A2

0 V

For the semiconductor outputs

(connector X2)
Must always be present, even if

the semiconductor outputs are not

used

24 V

+ 24 V DC

0 V

0 V

Supply voltage

6.3.3

6.3.3.1

6.3.3.2

6.3.4