Commissioning

Operating Manual PNOZ m1p (ETH)
20878-EN-12

20

Process data exchange

The RJ45 interfaces on the internal autosensing switch enable process data to be ex-
changed with other Ethernet subscribers within a network.
The product

m1p ETH can also be connected to Ethernet via a hub (hub or switch).

Ethernet

Hub/Switch

Hub/Switch

Ethernet subscriber

Ethernet subscriber

PNOZmulti base unit

with Ethernet interface

PNOZmulti base unit

with Ethernet interface

PC with PNOZmulti

Configurator

PNOZmulti as Ethernet subscriber - possible topologies

Preparing for operation

Function test during commissioning

ATTENTION!
It is essential to check that the safety devices operate correctly

– after the chip card has been exchanged
– after a project has been downloaded
– when the project has been deleted from the base unit's memory ("Re-

set Project" menu)