background image

Form I-VR, P/N 205202 R13, Page 13

FIGURE 12 -

Attaching Hanging

Chain at Tube

Suspension Points

6.2.3 Install the Heat

Exchanger Tubes

and Turbulator

Strip Sections

There are very important steps that must be followed to suspend and assemble

this tubular radiant heater. Suspension and field assembly are the responsibil-

ity of the installer. Follow all instructions carefully.
1. Identify the heat exchanger tubes and parts packaged with them (Refer to

the illustrations in

FIGURES 13A-13D).

Refer to illustrations

in FIGURES as noted.

Follow Steps in order.

2. Install the First Heat Exchanger Tube

a) Determine if the first heat exchanger tube is straight, “U”, or “L”. (See con-

figuration requirements, Paragraph 4.1, for placement of 5-ft, “U” or “L”

tubes.) If the first tube is a “U” or “L”, follow the instructions shipped with

the option package.

NOTE: Reflectors

shown here will

be installed after

all chains are in

place.

Hanger Bar

“S” Hook

Chain attached to suspension point.

FIGURE 13B - Heat Exchanger Tubes (Straight, “U”, and “L”)

Straight Heat

Exchanger Tube,

10 ft (3M) or 5 ft

(1.5M), Option

UA1

“L” Heat Exchanger

Tube, Option UC2

“U” Heat

Exchanger

Tube, Option UB3

FIGURE 13C - Tube Coupling with Tighten-

ing Bolts and Two Self-drilling Screws

(coupling has pre-punched holes; self-drill-

ing screws attach coupling to tubes and

vent pipe)

FIGURE 13D - One

Section of Field-Installed

Turbulator Strip

FIGURE 13A - Wire

Reflector Retainer,

Hanger Bar, U-Bolt

and Tube Bracket

Important NOTE: Before installation, wipe any excess corrosion inhibitor from the

heat exchanger tubes. Failure to do so could result in excessive smoke from the sur-

face of the tubes on first startup.

If installing a straight tube, prepare the tube by attaching a tube bracket

(See

FIGURE 14.) within 12” (305mm) of the downstream end of the tube.

Slide the threaded “U” bolt over the tube and through the bracket; attach

FIGURE 14 - Attach

the tube bracket and

wire reflector retainer

to the heat exchanger

tube.

Tube

Bracket

U Bolt

Nuts

“Hook” Wire Reflector

Retainer to Tube Bracket

(Metal hanger bar is not

illustrated. See

FIGURE 12.)

NOTE: One “hook” of the wire

retainer is bent 75° and the other

45°. If the reflector is going to be

rotated, be sure the side with the