beautypg.com

0 roof curbs for maps, Cabinets a, b, c (cont'd) – Reznor ADFH Option - Installation - Roof Curbs Assembly User Manual

Page 6

background image

Form I-OPT-C, Page 6

1.0 Roof Curbs for

MAPS

®

Cabinets

A, B, C (cont'd)

1.2 Curb for Vertical (Down) Airflow WITH an Optional Energy Recovery

Module, Option ER1A, ER1B, ER1C (Roof Curb Option CJ34) (cont'd)

Option CJ34 Roof Curb Corner Hardware (See FIGURE 2B)

For

Top Two

"Holes"

(16) 5/16" x 1" Lag Screws,

P/N 16243; (16) 5/16" Lockwasher, P/N 1333

For

Bottom

Two "Holes"

(16) 5/16" x 3/4" Hex Head Cap Screw,

P/N 16247; (16) 5/16" Lockwasher, P/N 1333;

(16)

5/16-18 Hex Nut, P/N 1035

Hardware to Assemble and Attach Dividers to make Duct Connections and Sealant Tape for Top of

Rails: (75) #10 Sheetmetal Screws, P/N 11813; (1) 1/4" x 1-1/4" x 50' Foam Sealant Tape,

P/N 66302

Installation Instructions

for Down Discharge

Roof Curb, Option

CJ34, for MAPS

®

Cabinet Sizes A, B,

and C WITH Energy

Recovery Module,

Option ER1

6. Before placing the MAPS

®

unit or energy recovery module on the curb:

If ductwork is being installed from the top, slide the ductwork down into the discharge and return air openings.

Ductwork should be sized slightly smaller with a minimum 3/4" duct flange that will rest on and be attached to all

sides of the duct connection. See the system installation manual for ductwork requirements.

Apply 1/4" x 1-1/4" foam sealant tape to both the top surface of the curb rails and the top surface of the perimeter of

the integral dividers, being sure to make good butt joints at all corners. The sealant tape must be applied to prevent

water leakage into the curb area due to blown rain and capillary action.

7. Lift the MAPS

®

unit on to the prepared curb (See Rigging and Lifting in the unit installation manual, Form

I-MAPSIII&IV).

IMPORTANT: Verify that the unit will be placed in the correct airflow orientation to mate properly

with the discharge and return air openings.

8. After the MAPS

®

unit is in place, follow the instructions shipped with the energy recovery module

(Form I-MAPSIII&IV-ER) to lift and mate the energy recovery module to the MAPS

®

unit.

9. Refer to the MAPSIII&IV installation manual and start up information to complete the installation.

14”

(356mm)

1-7/8”(48mm)

(102mm)

2 x 4 Wood

Nailer

1-1/2 x 3 lb

Fiberglass

Flashed by the

installer (flashing

must be under lip

of curb)

Lag Screw

Cap

Screws

Curb Detail

Corner Detail

Curb Section

1. Assemble the MAPS

®

Unit Curb Section (Refer to FIGURE 2A, page 5)

a) Position the ends and sides (

Codes B, B, A, and J

) of the MAPS

®

section of the

curb as shown in the drawing in

FIGURE 2A. Fasten with bolts and lag screws

as illustrated in the corner detail (

FIGURE 2B).

b) Install bottom opening ductwork. Use the sheetmetal screws to attach the

dividers (

Codes C1, C2, D1, D2, E, & F

in

FIGURE 2A). Attach the return air

duct angles (

Codes G & H) to the attached end and side and to the roof curb.

NOTE: If the system does not have a return air opening, Codes F, G, & H may

be installed in the curb but are not required.

2. Assemble the Energy Recovery Curb Section

a) Position the sides (

Codes L and M

) as shown in the drawing in

FIGURE 2A.

Attach the sides to the assembled curb section with sheetmetal screws.

b) Attach the curb end (

Code A

). Fasten with bolts and lag screws as illustrated in

the corner detail (

FIGURE 2B) .

c) Position the tunnel (

Code K

) over the opening in the center. Attach with sheet-

metal screws.

3. Check the roof curb for squareness. The curb must be adjusted so that the

diagonal measurements are equal within a tolerance of ±1/8” (±3mm).

4. Level the roof curb. To ensure a good weatherproof seal between the unit curb cap

and the roof curb, the roof curb must be leveled in both directions with no twist end

to end. Shim as required and secure curb to the roof deck before installing flashing

(See Curb Detail in

FIGURE 2B).

5. Install field-supplied flashing.

FIGURE 2B - Option

CJ34 Downflow Roof

Curb Cross Section and

Corner Detail

MUST be sealed

between curb cap

and top of curb

Cabinet

2x4 Wood Nailer

Counter Flashing

(by installer)

Cant Strip

(by installer)

Weld, bolt, or lag screw curb to deck structure.

Roofing Felts

(by others)

Insulation