beautypg.com

Carrier AQUASNAP MPW015-045 User Manual

Page 36

background image

36

This voltage imbalance is satisfactory as it is below the

maximum allowable of 2%.

Control Circuit Power — Power for the control circuit is

supplied from the main incoming power through a factory-

installed control power transformer (TRAN1) for all models.

Field wiring connections are made to the LVT.

OPERATION SEQUENCE

The unit is started by putting the ENABLE/OFF/REMOTE

CONTACT switch in the ENABLE or REMOTE CONTACT

position. When the unit receives a call for cooling (either from

the internal control or CCN network command or remote con-

tact closure), the unit stages up in capacity to maintain the leav-

ing fluid set point. The first compressor starts 1

1

/

2

to 3 minutes

after the call for cooling.

For all units, if temperature reset is being used, the unit con-

trols to a higher leaving-fluid temperature as the building load

reduces. If demand limit is used, the unit may temporarily be

unable to maintain the desired leaving-fluid temperature be-

cause of imposed power limitations.

SERVICE

Electronic Components

CONTROL COMPONENTS — Unit uses an advanced elec-

tronic control system that normally does not require service.

For details on controls refer to Operating Data section.

Access to the controls is through a hinged panel. Inner pan-

els are secured in place and should not be removed unless all

power to the chiller is off.

Compressor Replacement —

All models contain

scroll compressors and have two or three compressors. A com-

pressor is most easily removed from the side of the unit or

above, depending on where clearance space was allowed dur-

ing unit installation. See Fig. 21.

Remove the junction box cover bolts and disconnect the

compressor power and crankcase heater connections (30MPA

only). Remove the cable from the compressor junction box.

Remove the connections from the high-pressure switch. Re-

move the crankcase heater. Knock the same holes out of the

new compressor junction box and install the cable connectors

from the old compressor.

The compressors are bolted to rails, which are in turn bolted

to the unit basepan for all sizes. Remove the 4 bolts holding the

compressor to the rail on the basepan. Save the mounting hard-

ware for use with the new compressor. Carefully cut the com-

pressor suction and discharge lines with a tubing cutter as close

to the compressor as feasible. Remove high-pressure switch

and pressure transducer(s) if required for compressor removal.

Lift one corner of the compressor at a time and remove all the

steel spacers. Remove the old compressor from the unit.

Slide the new compressor in place on the rails. Lifting one

side of the compressor at a time, replace all of the compressor

mounting hardware. Using new tubing as required, reconnect

compressor suction and discharge lines. Using hardware saved,

reinstall the mounting bolts and washers through the compres-

sor feet. Using proper techniques, braze suction and discharge

lines and check for leaks. Reconnect oil equalization line.

Re-install the crankcase heater (30MPA units). Reconnect

the compressor power connections and high-pressure switch

wiring as on the old compressor. Refer to Fig. 21. Following

the installation of the new compressor, tighten all hardware to

the following specifications. (See Table 30.)

Table 30 — Unit Torque Specification

30MPW Condenser and 30MP Cooler

BRAZED-PLATE COOLER AND CONDENSER HEAT

EXCHANGER REPLACEMENT — Brazed-plate heat ex-

changers cannot be repaired if they develop a leak. If a leak

(refrigerant or water) develops, the heat exchanger must be

replaced. To replace a brazed plate heat exchanger:

1. Disconnect the liquid-in and liquid-out connections at the

heat exchanger.

2. Check that the replacement heat exchanger is the same as

the original heat exchanger. For the condensers, compare

part numbers on the heat exchangers. For the coolers, in-

sulation covers the manufacturer’s part number. Make

sure the depths of the replacement and original cooler

heat exchangers are the same.

3. Recover the refrigerant from the system, and unsolder the

refrigerant-in and refrigerant-out connections.

4. Remove the four nuts holding the heat exchanger to the

brackets. Save the nuts.

5. Install the replacement heat exchanger in the unit and at-

tach to the bracket using the four nuts removed in Step 4.

For sizes 015 and 020, torque is 7-10 ft-lb. For sizes 030-

045, torque is 35 to 50 ft-lb.

6. Carefully braze the refrigerant lines to the connections on

the heat exchanger. Lines should be soldered using silver

as the soldering material with a minimum of 45% silver.

Keep the temperature below 1472 F (800 C) under nor-

mal soldering conditions (no vacuum) to prevent the cop-

per solder of the brazed plate heat exchanger from chang-

ing its structure. Failure to do so can result in internal

or external leakage at the connections which cannot be

repaired.

7. For coolers, ensure that the original size tubing is used

(

1

/

2

-in. for sizes 015 and 020 and

5

/

8

-in. for sizes 030-045)

between the TXV and the cooler. The TXV must be lo-

cated within 1 ft of the heat exchanger, with no bends be-

tween the TXV outlet and the cooler inlet.

8. Reconnect the water/brine lines.
9. Dehydrate and recharge the unit. Check for leaks.

BRAZED-PLATE COOLER AND CONDENSER HEAT

EXCHANGER CLEANING — Brazed-plate heat exchang-

ers must be cleaned chemically. A professional cleaning ser-

vice skilled in chemical cleaning should be used. Use a weak

acid (5% phosphoric acid, or if the heat exchanger is cleaned

frequently, 5% oxalic acid). Pump the cleaning solution

through the exchanger, preferably in a backflush mode. After

cleaning, rinse with large amounts of fresh water to dispose of

all the acid. Cleaning materials must be disposed of properly.

IMPORTANT: If the supply voltage phase imbalance is

more than 2%, contact your local electric utility company

immediately. Do not operate unit until imbalance condition

is corrected.

WARNING

Electrical shock can cause personal injury and death. Shut

off all power to this equipment during service. There may

be more than one disconnect switch. Tag all disconnect

locations to alert others not to restore power until work is

completed.

FASTENER

RECOMMENDED TORQUE

Compressor Mounting
Bolts

7 to 10 ft-lb (9.5 to 13.5 N-m)

Compressor Power
Connections

24 to 28 in.-lb (2.7- to 3.2 N-m)

Compressor Ground
Terminal Connections

14 to 18 in.-lb (1.6 to 2.0 N-m)