beautypg.com

Harrington Hoists and Cranes RHN - Rhino Wire Rope Hoist User Manual

Page 22

background image

22

3.4

Assembly, Adjustments and Mounting



When installing the trolley hoist on a beam, ALWAYS raise the hoist into position with the

trolley assembled together and securely attached to a pallet. Raise the trolley hoist with a forklift, lifting platform,
or other similar means. NEVER use slings to raise and install the trolley hoist onto the beam (see

Figure 3-4

).

Using a forklift or another suitable means, position the pallet so that the horizontal axis of the beam is parallel to
the horizontal axis of the hoist (see

Figure 3-5

)

Note: Unless specified when ordered, the RHN Trolley hoist is factory set to accommodate a 12 inch (306mm) beam
flange. If a smaller flange width is necessary, the driveshaft position and/or length may require a change as well (See

Table 3-1).

If the supplied trolley drive shaft is too long for the desired flange, a short trolley drive shaft can be ordered, or

the existing shaft can be cut down to the appropriate length. Use caution and always wear eye protection when cutting
the trolley drive shaft with a powered saw or a manual saw. Deburr the cut end of shaft before reinstalling. The RHN is
equipped with the maximum number of counterweights necessary for the standard (advertised) flange range for each
capacity. If the flange range exceeds 12 inches (306mm), some counter weight may need to be removed to achieve
proper balance.

3.4.1

RHN Trolley Hoist Installation

1) Make sure the mounting location complies with

Section 3.3

.

2) Before attempting to install the trolley hoist, verify beam width and the “c” dimension (see

Figure 3-6

).

See

Table 3-1

for dimensions respective values.

If adjustment is not necessary, move onto section

Section 3.4.1 (step 8).

If adjustment is necessary move onto

step 3, below

.

3) Determine the correct driveshaft length for your application.

a. If a shorter driveshaft length is required, it is necessary to replace or cut the existing driveshaft to the

appropriate length. (See

Table 3-2)

b. If a longer driveshaft length is required, it is necessary to replace the existing driveshaft with one of

the appropriate length. (See

Table 3-2)

4) Determine the correct Snap Ring Position on the driveshaft, for your application. (2 ton – 10 ton)

Each driveshaft has multiple Snap Ring positions shown as X3 and X4. These different positions allow
the Trolley Driveshaft to be inserted at two different depths within the motor housing. This gives the
drive shaft the ability to accommodate a range of beam flange widths before it necessary to change the
shaft length.(See

Table 3-2)

5) Accessing the Drive Shaft for replacement, shortening and/or Snap Ring relocation.

a. Carefully remove the trolley motor by loosening and removing the 4 trolley motor mounting bolts. It

may be necessary to disconnect the trolley motor cable, if there is not enough slack to allow for the
motor to be safely supported, as work is being performed. With the bolts removed, the motor can
slide off of the drive shaft.

b. With the motor removed and safely placed out of the way, the driveshaft can pulled out of the trolley

assembly.

6) Adjust the trolley flange to fit beam width.

a. Working on the trolley motor side of the hoist, (the side closest to the large rectangular counter

weights), loosen the nuts (2) on the two threaded shafts (1) of the trolley hoist. DO NOT loosen the
nuts closest to the hoist. NEVER move the hoist side of the trolley. (See

Figure 3-6 and Figure

3-11)