Note: For vertical fan-coil units, push the main condensate drain

hose and overflow condensate drain hose through to the inside of the

chassis end panel to prevent them from being burned when making

sweat connections. Be sure to pull the hoses back through and route

to the auxiliary drain pan when the end panel has cooled.

3. Solder the joint using bridgit lead-free solder (ASTM B32-89) to

provide a watertight connection. Avoid overheating factory soldered

joints when soldering field connections to the coil to prevent

leakage from occurring.

4. Insulate all piping to coil connections as necessary after connec-

tions are complete.

Note: Maintain a minimum distance of one foot between the reduction

fitting for the 1/2 inch diameter line and the fan-coil unit piping

connections.

Install the auxiliary drain pan, which ships in the accessory packet

CAUTION: In all steam coil installations, the con-

densate return connections must be at the low point of
the coil to ensure condensate flows freely from the coil
at all times. Failure to do so may cause physical coil
damage from water hammer, unequal thermal stresses,
freeze-up and/or corrosion.

1. Make piping connections to the steam coil as shown in Figure 7.

Cap the unused connection.

2. The coil is already pitched within the unit to provide proper pitch to

drain condensate out of the coil. Ensure that the unit has been

properly leveled. Refer to page 13 for unit leveling instructions.

3. Install a 1/2 inch, 15-degree swing check vacuum breaker in the

unused condensate return tapping as close as possible to the coil.

Units with Steam
Coils

!

Figure 7. Steam coil header ports. The center port is the supply
connection. The return port is below the supply. The top port