6 Commissioning
6.1 Commissioning the Inverter
1. Check the following requirements before commissioning:
– The inverter is securely in place
– The AC cable is correctly connected (power distribution grid)
– All DC cables connected (strings)
– Unused DC inputs are closed using the corresponding DC connectors and sealing plugs
– The enclosure lid is securely screwed in place
– The Electronic Solar Switch is securely plugged
– The miniature circuit-breaker is correctly laid out
2. Switch on the miniature circuit-breaker.
☑ All 3 LEDs are glowing or blinking: The startup phase is starting.
☑ Green LED glows: commissioning has been successful.
or
☑ Green LED flashes in case of insufficient irradiation: grid connection conditions have not yet
been reached. Wait for sufficient irradiation.
or
☑ The red or yellow LED is glowing or flashing: a disturbance has occurred. Proceed to step 3.
3. Read section 9 "Troubleshooting" (page 66) and if necessary eliminate the fault or disturbance.
A Green LED
Operation
B Red LED
Ground fault or varistor
defective
C Yellow LED
Fault
Self test in accordance with DK 5940, Ed. 2.2 for initial commissioning
(applies to Italy only)
The Italian DK 5940 standard prescribes that an inverter can only operate on the power
distribution grid after the disconnection times for overvoltage, undervoltage, minimum
frequency and maximum frequency have been checked.
Start the self-test as described in section 6.3 "Self-Test in Accordance with DK 5940, Ed. 2.2
(Applies to Italy Only)" (page 51). The test takes approx. 8 minutes.