2 cabling, Cabling – SMA SMC 7000HV Installation User Manual

Page 42

background image

Electrical Connection

SMA Solar Technology AG

42

SMC70HV11-IA-IEN112970

Installation Manual

• PowerGuard

This setting can be selected if the entire PV plant only consists of three Sunny Mini Central
inverters and in the event of a malfunction, the unbalanced load should be limited to 4.6 kVA
over a 10-minute average.

If one of the 3 inverters indicates a grid voltage fault or device fault and stops feeding in,
the other two inverters automatically limit their power to 4.6 kVA over a 10 minute average.

5.5.2 Cabling

Cable Requirements

For cabling the SMA Power Balancer, use a "LiYCY" cable, structured as shown here:

• Indoor: LiYCY 2 x 2 x 0.25
• Outdoor: Li-2YCYv 2 x 2 x 0.25

Deviating unbalanced load limit for Italy
The unbalanced load for inverters set to the Italian national standard DK 5940 is limited
to 6 kVA over a 10-minute average.

Position

Description

A

Flexible insulation

B

Shielding

C

Twisted pair 2 (2 x 0.25 mm²)

D

Twisted pair 1 (2 x 0.25 mm²)