Commissioning (Installer)

SMA Solar Technology AG

20

BeamBT11-BA-BEN112713

User Manual

Prior to commissioning, familiarize yourself with the operating principle of the Sunny Beam
(see section 5.1).
Sunny Beam will guide you through the commissioning procedure. After commissioning, configure the
first settings in the Sunny Beam (see section 6.2).
Procedure:

• Configure the basic settings
• Search for your plant
• Set the plant time and plant power

Configure the basic settings

1. Open the underside of the accumulator compartment.
2. Insert accumulators into the accumulator compartment. For this purpose, observe the marking in

the accumulator compartment.
Tip: You do not have to load the accumulators in advance. Sunny Beam loads the accumulators
using a PV cell.

3. Close the accumulator compartment.

☑ The start screen appears.