Connecting the wires in the junction box, Testing/checking operation, 3 set the voltmeter to read ohms – Gasboy M06245K0XX User Manual
Page 19: Completing the installation

MDE-4506A Atlas™ Pulser Kits M06245K0XX Installation · May 2006
Page 19
Installing the Pulser Kit in Single Unit and 9140 (Kits M06245K004 through M06245K007 and M06245K009 - M06245K011)
6
Loosely secure in place with two washers and two screws.
7
Ensure that the parts are meshed properly and tighten the screws.
8
Ensuring that the wires extend through the conduit, make the necessary connections as shown
in
or
.
9
Ensure that the wires extend into the junction box.
Connecting the Wires in the Junction Box
1
Remove the screws securing the cover on the junction box. Save screws for remounting.
2
Inside the junction box, connect the green ground lead from the pulser to a secure known
ground.
3
Refer to your Fuel Management System installation manual for proper wiring of the pulsers.
4
Remount the junction box cover and secure it with the screws removed in
.
Testing/Checking Operation
Only the 10:1 pulser can be tested for operation. Using test equipment, others must be tested
when hooked to the pump/dispenser controller. Test the 10:1 pulser as follows:
1
Inform the manager/owner that power will be restored to the unit and then restore power to the
unit.
2
Connect a mechanical voltmeter on the two orange signal wires.
3
Set the voltmeter to read Ohms.
4
Slowly dispense fuel and observe that the needle deflects upscale for each 1/10 gallon fuel.
Completing the Installation
1
After determining that the pulser is functioning properly, remount the dial faces on the
computer and secure them with the screws saved during removal.
2
Remount the bezels on both sides of the unit and secure them with the screws saved during
removal.
3
Remount the doors on both sides of the unit and secure them with the keylocks.
4
Inform the manager/owner that the unit can be returned to service.