Operation • 2, Run a trial piece, Start machine operation – Pitney Bowes DI425 FastPac Inserting Systems User Manual
Page 19
![background image](/manuals/740556/19/background.png)
Operation • 2
2-3
SV61656 Rev. A
Run a Trial Piece
Once material is in place, press
Trial Piece so you can check that
setup is correct.
You can make minor changes to the job settings at this stage if the
trial piece needs fine tuning. Enter setup as described on page
2-9, then use the
Prev (◄), Next (►) and Change (+/-) buttons as
required to modify job settings. When you’ve made the necessary
changes, press
Setup again to return to run mode. The inserter
saves the job with the new settings.
Notes:
1. When using linked feeding,* load both sheet feeders before run-
ning a trial piece.
2. If you load material during a run which seems to have different
characteristics (weight, color shade, etc.), or if you have any
problems with double detection, run another trial piece. This
forces the machine to recalibrate the double detect function for
the new material in case the batches vary slightly.
Start Machine Operation
Press
Start to begin automatic operation.
The machine runs until either material runs out or you press the
Stop button.
Note: If the machine is set for linked feeding, the display shows:
1 > 2 > 1
This confirms that feeding will automatically switch between
sheet feeders. See page 2-13 for more details.
* “Linking” is a method of using two feeders such that when one feeder
runs out of material, the next “linked” feeder automatically starts feeding.
Linking feeders allows you to process a higher volume of material before
reloading. Linked feeders are sometimes referred to as “cascading”
feeders.