9 Vertical - Flue Length, Preparation and Installation

12969

Diagram 9.19

9.12 Flue Installation

Refer to diagram 9.20 and secure the flue adapter in position

on top of the boiler with four screws supplied,

NOTE: The rubber ‘O’ rings of each section should be

lubricated prior to assembly. Do not use mineral oils or

grease, silicon grease or water is recommended.

Secure the first extension pipe to the flue adapter with the

securing collar supplied by positioning the collar centrally over

the joint, then tighten the two screws on the securing collar,

see diagram 9.21.

Fit more extension pipes as required using the collar and

screws supplied with each extension pipe. To fit position the

collar centrally over the joint, tighten the two screws on the

securing collar. Using the holes provided in the securing

collar drill and insert the two self tapping screws supplied, see

diagram 9.22.

The rubber ‘O’ rings of each section should be lubricated prior

to assembly.

NOTE: Do not use mineral oils or grease, silicon grease or

water is recommended.

When installing the flue it is recommended that it is supported

every 2 metres and at every bend by a fixing bracket.

Project the rise of the flue pipe to roof level and cut a 150mm

hole in the roof.

9.13 Flue Terminal Installation

(a) Pitched Roof

Fit the required pitched roof weather collar over the 150mm

hole in the roof. Make good the tiling or slating around the

collar incorporating the flashing of the weather collar. Position

the angle cap over the weather collar in the correct orientation

to attain the correct angle for your roof.

(b) Flat Roof

Fit the aluminium weather collar over the 150mm hole in the

roof ensuring a weather tight seal.

From above carefully place the flue terminal through the

weather collar.

9.14 Flue Terminal to Boiler Connection

Should the clearances above the boiler to roof not allow for

extensions, it is permitted to cut the flue terminal ensuring the

relationship of flue and air duct lengths are retained.