6 Installation Preparation

Diagram 6.3

14549

6.3 Wall Template

Take the wall template from the document pack and place in

the desired position on the wall, giving due consideration to

the required boiler clearances, see section 3, and the flue you

are fitting.

Mark the position of the flue centre, if fitting a side flue, extend

the flue centre line into the corner then 170mm along the

adjacent wall, see diagram 6.3.

For extended side flues, the flue hole centre should be

determined by extending the dashed inclined line on the

template to the side wall, then 149mm along the adjacent

wall, see diagram 6.2. This dashed line is drawn at 44mm/

metre (2.5°) rise from the boiler.

To allow for the flue passing through the wall at this angle

a 125mm hole should be drilled irrespective of internal or

external installation.

Remove the wall template whilst drilling the flue hole.

6.4 Flue Hole Cutting

External access flue installation can use a 105mm diameter

core drill.

Internal access only flue installation will need a 125mm

diameter core drill.

NOTE: The flue is designed with an internal fall of 44mm/

metre (2.5°), therefore the hole can be drilled horizontally.

If flue extension pipes are to be used then a core drill size of

125mm is required. This will allow the extension pieces to

slope at 44mm/metre (2.5°) towards the boiler.

6.5 Wall Hanging Bracket Assembly

The Wall Hanging Bracket is supplied in the main boiler

packaging.

Reposition the wall template over the flue hole and mark the

position of the fixing holes for the hanging bracket.

NOTE: Due to the varied site conditions we do not supply

fixings and advise that the installer should supply those which

are suitable.

Drill fixing holes using a 8.5mm. drill bit and insert suitable

wall plugs. Secure the wall hanging bracket to the wall.