5) Steady Heat - Control inputs are continuously monitored to ensure limit and pres-

sure switches are closed, flame is established, and the thermostat call for heat remains.

When the thermostat call for heat is removed, the control de-energizes the gas valve

and begins post-purge and fan/blower off delay timing.
6) Post Purge - The venter motor output remains on for a 45-second post-purge period

after the thermostat is satisfied.
7) Fan/Blower Off Delay - The fan/blower motor is de-energized after a blower off

delay of 120 seconds:

Interrupted Thermostat Call for Heat - If the thermostat demand for heat is removed

before the flame is recognized, the control will run the venter motor for the post purge

period and de-energize all outputs.
If the thermostat demand for heat is removed after successful ignition, the control will

de-energize the gas valve, run the venter motor through post purge, and run the fan/

blower motor on heat speed for the selected delay off time.
Ignition Retry - If flame is not established on the first trial for ignition period, the control

de-energizes the gas valve and the venter motor remains energized for an inter-purge

period of 10 seconds. The spark and gas valve are then re-energized, and the control

initiates another trial for ignition.
If flame is not established on the second trial for ignition, the control de-energizes the

gas valve, energizes the fan/blower motor on heat speed, and venter motor remains

energized. The fan/blower motor is shut off after 120 seconds. When the fan/blower

motor de-energizes, the spark and gas valve are re-energized and the control initiates

another trial for ignition. (This blower delay is self-healing feature for an open auxiliary

limit switch).
If flame is not established on the third trial for ignition period, the control de-energizes

the gas valve, and the venter motor remains energized for an inter-purge period of 10

seconds. The control then re-energizes the gas valve and spark and initiates another

trial for ignition.
If flame is not established on the fourth trial for ignition (initial try plus 3 re-tries), the

control de-energizes the gas valve and goes into lockout. The control goes to one flash

on the green LED to indicate ignition failure lockout.
Limit Switch Operation - The limit switch is ignored unless a call for heat is present

(W energized). If the limit switch is open and a call for heat is present, the control de-

energizes the gas valve and turns the fan/blower motor on heat speed and runs the

venter motor. The control will be in soft lockout and flashing fault code “3” before return-

ing to normal operation.

When the switch re-closes or the call for heat is lost, the control runs the venter motor

through post purge and runs the blower/fan motor through the selected fan off delay.
Pressure Switch - If the pressure switch opens before the trial for ignition period, the

venter motor will run through the pressure switch recognition delay (2 seconds), the

gas valve will be de-energized, and the venter motor will run through the postpurge

time. The control will re-start the heat cycle at the pressure switch proving state if the

call for heat still exists.
Pressure switch opening for less than 2 seconds during the trial for ignition period shall

not interrupt the heat cycle. (Gas valve will de-energize while the pressure switch is

open.)
If the pressure switch opens after a successful ignition, the control will de-energize the

gas valve. If flame is lost before the end of the 2 second pressure switch recognition

delay, the control will respond to the loss of flame. If the pressure switch remains open

for 2 seconds and the flame remains, the control de-energizes the gas valve, the venter

motor runs through post-purge, and the fan/blower motor runs on heat speed through

the selected blower off delay. When the blower off delay is over, the fan/blower motor

is de-energized, and a heat cycle is begun if the call for heat still exists.

Abnormal Heat Cycle

Functions

8.0 Controls and

Operation

(cont’d)

8.3 Ignition System

(cont’d)

Normal Heat Cycle Operating Sequence (cont’d)

This manual is related to the following products: