Dynon Avionics SkyView System Installation Guide User Manual
Page 190
SV-GPS-250 Installation and Configuration
8-4
SkyView System Installation Guide - Revision S
If there is more than one SV-GPS-250 in your system, use the same scheme in Figure 56 on
different display serial ports for the other SV-GPS-250 modules, but connect power and ground
for the other SV-GPS-250 modules to the same power and ground connections (black and
orange wires) that are provided in the serial port 5 wiring bundle on the display harnesses. An
example of this configuration follows.
Figure 57 – Dual SV-GPS-250 Connected to Multiple Displays
Configuration
Go to the Serial Port Setup Menu (SETUP MENU > SYSTEM SETUP > SERIAL PORT SETUP>SERIAL
PORT 5 SETUP) and then configure serial port 5 as follows:
SERIAL IN DEVICE:
Dynon SV-GPS-250
SERIAL IN FUNCTION:
POS 1
SERIAL IN/OUT BAUD RATE:
38400
SERIAL OUT DEVICE:
NONE
If you have multiple SV-GPS-250 modules, connected as shown above, you must
configure the second serial port (serial port 4 if done as shown) as an SV-GPS-250
as well. Its SERIAL IN FUNCTION should be set to POS 2.