beautypg.com

B&C Technologies DI-325 Industrial User Manual

Page 73

background image

OPERATING AND PROGRAMMING INSTRUCTIONS

8-42

9.2 Install infra red sensor option

The IR expansion kit is supplied with the following parts:

























6. Infra-red sensor
7. Expansion board for IR sensor interface


Installation in a machine

1. Switch off the machine and disconnect the power.
2. Mount the infra-red sensor (6) in the correct position in the machine. The sensor must point

downwards to the middle of the drum.

3. Install the expansion board (7) on the back of the controller. The connector for this is

located next to the battery holder. Make sure that the pins are aligned correctly, and the
plastic supports are aligned with the holes in the controller board to avoid damaging the
expansion board or the controller.

4. Reconnect the power and enable the IR sensor in the controller. (chapter 6.8, parameter 5)
5. Change the programs for which you wish to use automatic drying. (chapter 6.4.1, parameter

1)


NOTE: It is not possible to install the infra-red sensor in combination with the humidity sensor
(9.3) as they both require use of the same expansion connector on the DQ 01 Dryer
Controller board.