beautypg.com

Landoll HSB 71-1 through 131-1 SOIL BUILDER Coulter Chisel - Extended Frame User Manual

Page 19

background image

1K705

9-SHANK WALKING BEAM

Position the wheel arm assemblies under the

frame as shown in Figure 2a-T and 2b-T. Note that

the inner wheel hubs are rearward of the machine

and the shorter end of the wheel arm pivot tube is

toward the outside of the machine.

Take the six bearings (7J627) and coat the inside

bearing surfaces with grease.

Center the rockshaft, with the link ears rearward,

on top of the frame directly above the wheel

arm assemblies as shown in Figure 2a-T. Place

a bearing (7J627) on each end of the rockshaft

above the 10 x 4 frame tube aligning them with the

appropriate set of holes.

7J627 Bearings

HHCS, 3/4-10NC x 6 1/2”

Lock washers, 3/4”

3/4-10 Nuts

7J627 Bearings

Page 17

HHCS, 3/4-10NC x 6

Lock washers, 3/4”

3/4-10 Nuts

Wheel Arms

791rev5-30-05

Place a bearing (7J627) per wheel arm and

place one on each end of wheel arms pivot tube.

Position the assembly under the 10 x 4 frame

tube with the inner bearing in the inner most set

of holes. Verify that the rockshaft link ears line

up with the wheel arm link ears. Bolt this bearing

in place with 3/4-10NC x 6” capscrews, lock

washers and nuts. The other bearing should line

up with top bearing used for the rockshaft (3rd

set of holes). Bolt this bearing in place with 3/4-

10NC x 6-1/2” capscrews, lock washers and nuts.

(Hardware is in box 1K691)

7J627 Bearings

7J627 Bearings

(Use this position

for 9-shank)

Rockshaft

IMPORTANT!

Coat all bearing surfaces with

grease before installing.

9-SHANK

Alignment

TANDEM WALKING BEAM ASSEMBLY

Figure 2a-T

9-SHANK

This manual is related to the following products: