beautypg.com

System startup, 1 check system connections, 2 verify ac and power the rectifier shelf – Alpha Technologies Cordex CXPS-M 48_24-1200_600A User Manual

Page 53: 3 check battery polarity and connect, 4 final configuration and test

background image

51

9400004-J0 Rev B

7. System Startup

Visually inspect the installation thoroughly. After completing the system installation and power system wiring, per-

form the following startup and test procedure to ensure proper operation:

7.1 Check System Connections

1. Make sure that the AC input power is switched off, the batteries are disconnected, and all the power modules

are removed from the shelf.

2. Triple-check the polarity of all connections.

7.2 Verify AC and Power the Rectifier Shelf

1. Install one power module.
2. Verify that the AC input voltage is correct and switch on the corresponding feeder breaker. The power

module OK LED will illuminate after a preset start delay.

7.3 Check Battery Polarity and Connect

1. Use a voltmeter to verify that the battery polarity is correct. Ensure that no cells or batteries are reversed.
2. Connect the batteries or switch on the battery circuits.
3. Install the remaining power modules.
4. In the adjustments menu of the CXC, set the float and equalize voltages to the levels specified by the battery

manufacturer.

7.4 Final Configuration and Test

1. Configure other system parameters as required—changing the low and high voltage AC and DC warning and

cutout limits, for example.

2. At this point there should be no alarms present. Investigate and correct any alarm issues.
3. Test the functionality of various alarms and controls as follows:

Alarm

Test

Minor alarm

To simulate a minor alarm, shutdown one rectifier.

Major alarm

To simulate a major alarm, shutdown two rectifiers.

AC Fail alarm

Turn off all AC breakers and run on batteries.

Supervisory Fail

At the controller, tap the Home icon at the lower left of the “home” page and select

Reset from the pop-up menu.

4. Perform a system load test using a resistive load box.
5. Turn off the AC input breaker to perform a full load test from DC power.
6. Enable the temperature compensation (temp comp) feature in the batteries menu. Program the settings for

slope and breakpoints (upper and lower) according to the specific batteries used.

This manual is related to the following products: