Install intermediate handrails – Grain Systems Bucket Elevtors, Conveyors, Series II Sweeps PNEG-1807 User Manual

Page 75

background image

10. 4 x 5 Distributor Platform (Optional)

PNEG-1807 16"-24" Bucket Elevator Platform and Ladder “X” Series

75

Install Intermediate Handrails

1. Insert small intermediate handrail into the large intermediate handrails to create telescoping rails.

Cut 30" off one small intermediate and one large intermediate rail to fit at entrance. Adjust all rails to
the proper length and install to the posts using the 5

th

hole down from the top. Fasten in place using

two (2) 5/16" x 3/4" flange bolts and nuts per each telescoping tube.

(See Figure 10M.)

Figure 10M