8. 16"-24" Head Platform Assembly

PNEG-1807 16"-24" Bucket Elevator Platform and Ladder “X” Series

59

2. Trim two (2) large and two (2) small rails by 15" each so that the remaining length of each rail, both

small and large, is 21".

(See Figure 8S.)

a. Install these rails across the Deck A, Deck C, Deck E side of the platform and the opposite side

as shown.

b. Insert one small rail inside of one large rail and telescope the joined rails from the “W” corner post

to the platform post as shown in

Figure 8R on Page 58

.

c. Attach to “W” posts (corner posts) and platform posts using nuts (S-3611) and bolts (S-6066).

d. Torque to standard specifications.

Figure 8S 21" Telescoping Handrail

3. Trim two (2) large and two (2) small rails by 4" each so remaining length of each rail, both small and

large, is 32".

(See Figure 8T.)

a. Install these rails across the up-leg and down-leg sides of the platform as shown.

b. Insert one small rail inside of one large rail telescope the joined rails from the “W” corner posts

to platform posts as shown in

Figure 8R on Page 58

.

c. Attach to “W” posts (corner posts) and platform posts using nuts (S-3611) and bolts (S-6066).

d. Torque to standard specifications.

Figure 8T 32" Telescoping Handrail